c

Efficient, effective construction

BIM has the power to bring building projects to life, helping to drive the delivery of more efficient processes and reduced risk. This includes at The Monument Building, a £33 million development that will bring 8175sqm of Grade A office accommodation and 370sqm of retail space to a site in the Square Mile.

Our work in action: The Monument Building

Through BIM we have been able to deliver measurable cost and time savings for the client. A complex 10-storey commercial development in a high profile location, Skanska has employed a full-time BIM Manager to oversee the implementation of best practice BIM techniques, leading to fantastic results.

Cost savings

We provided our steelwork subcontractor with an accurate model on which to base the steelwork designs. The ability to provide such highly sophisticated models had not previously been possible due to software incompatibility. Working with the BIM model proved to be much faster and reduced the opportunity for human error. The highly accurate designs translated into accurate construction, with only 0.5% spent on variations – an excellent result on such a complex build.

Further savings are made through coordinated temporary protection design. A review of the model revealed 81 instances where the position of cladding brackets on temporary edge protection would clash with cast concrete posts. This equated to 11.5% of the total number of brackets on the project. These clashes, which were not evident in the 2D drawings, could be designed out before construction began, realising significant cost and time savings.

Reduced requirement for diamond drilling

Skanska’s building and engineering teams collaborated in the design phase to identify where access, services and utilities holes could be incorporated into the precast concrete. This reduced the need for personnel to work onsite with diamond drills, leading to time and cost savings while also providing a safer working environment.

Clash prevention

More than a hundred hard and soft clashes between services and the main structure were cost-effectively resolved at the design stage. This included a significant clash between our concrete works and an adjacent building’s party wall, which was not evident in the 2D drawings but was identified once laser scans of the site were incorporated in the model. If not caught in the design phase, this single clash could have delayed the schedule.

Last updated: 23/01/2017